The evaluation of the bids will be multi-staged.
The first stage is a completeness check where bids will be reviewed to ensure that they are complete and nothing has been missed. Bidders will be given an opportunity to replace any missing elements.
The first pass of true evaluation comes in Stage 2.
In this Stage bids will be evaluated with respect to the Technical (how well the proposals meet Canada’s technical requirements) and Value Proposition (the quality of the bidder’s commitments to bring benefits to Canada and to incorporate Canadian content into the CSC design) elements of their bids.
During this evaluation bidders will need to demonstrate compliance with the identified Mandatory Compliance criteria and conformance with the other required criteria. Bids will be scored in accordance with the Evaluation Plan.
Again in the interests of maximizing the competition we will give any bidder that has not demonstrated compliance or conformance an opportunity to fix their proposal, a process we refer to as the Cure Process. This Cure process will be conducted in the following manner:
As evaluation teams complete each section of evaluation, feedback will be provided to each of the bidders regarding their bid. This feedback will explain what areas of the bid were found to be non-compliant or non-conformant and why. Bidders will be able to ask questions regarding the feedback they receive
Once all the sections of Technical and Value Proposition evaluation are completed and the final feedback has been provided to bidders the Final Submission Deadline will be established and communicated to bidders This date will be at least 4 weeks after the final feedback. During this period Canada and Irving Shipbuilding will respond to any questions asked regarding the bid feedback provided
On the Final Submission Deadline bidders will need to resubmit the affected portions of their bids and will need submit their financial proposals
The evaluation teams will then do the required re-evaluations based on the updated bids
There will only be one pass through the Cure Process
Any bidder that is still deemed non-compliant with any of the identified Mandatory Compliance criteria after the Cure Period will be eliminated from the competition.
If at least one bidder is compliant and has demonstrated conformance with all the other required criteria then those bidders’ scores will be considered final and the evaluation process will continue with Stage 2 score weighting using these scores. In this scenario any non-conforming bid will be set aside.
However, if after the Cure Process none of the compliant bidders have demonstrated full conformance with all the required criteria then non-conformance adjustments will be made to each of the compliant bids’ corresponding technical risk scores and the evaluation process will continue with Stage 2 score weighting using these adjusted scores.
The resultant Stage 2 scores of compliant bids will be weighted 75% Technical /25% Value Proposition (the highest Value Proposition weighting to date) and the top 2 bids (plus any that are very close) will move on to the next stage of evaluation.
The other bids will be set aside.
Those bids that have passed through will be scored for the remaining evaluation elements of Design Maturity, Software Capability and Financial.
Each bid’s raw scores for Technical and Value Proposition from the earlier stage will be retained and reweighted.
All the Stage 3 scores will be weighted and added together to get the bidder’s Total score. The final weightings will be Technical 42%, Value Proposition 15%, Design Maturity 19%, Software 1%, and Financial 23%.